• Power Station

 

 

 

 

 

 

 

 

 

 





ADMINISTRATIVE BUILDING & WAREHOUSES
  Project Manager :
The SOCOCIM
(
Commercial Company of Cement Factory )



Stage 1 : Preparation of the plateform




Stage 2 : Excavations





Stage 3 : Installatio, of the formwork of the solid masses

Stage 4 : Installation of the frame and casting of the solid masses



 


Stage 5 : Casting of the complements of dice for the foundation of the frame


Stage 6 : Installation of the cover





Stage 7 : Installation of the foundation
of the gasoil tank


Stage 8 : Installation of the wall of protection
of the gasoil tank






Stage 9 : External opening of the
power station


Stage 10 : Discharge






Stage 11 : Electrical power box


Stage 12 : Various conduits







Stage 13 : External Frontage of
the power station


Stage 14 : Main entrance of the
power station